Use of gantry cutting equipment: mainly used for cutting scrap steel.

 

Two, gantry cutting equipment composition: main engine, feed box, hydraulic system, electronic control system.

 

Three, gantry shear equipment parameters: specific reference technical agreement.

 

4. Basic work process: Start the motor of the oil pump - the motor is switched from the start mode to the running mode - the working parts return to the starting position in manual mode (the material cover is opened, the material is pushed in the back limit, the material is pressed and cut in the upper limit position) - Fill the appropriate amount of material into the material box - press the automatic start (" automatic open "of the remote control) the gantry cutting equipment will complete an automatic working cycle: Material cover close - material cover micro back - push material into (set on demand, Decided to shear ChengLiao length), under the pressure of material, under shear, cut, pressure micro - cut back - pressure back material back, pushing into, under the pressure of material, under shear, cut (not cut, cut back, cut down -- the reciprocating three times) - the back pressure is expected to micro - cutting back - pressure feeding back - cycle until the push that push material limit, At this time, the FCL material has been cut - cut back to the upper limit - press the material back to the upper limit - push the material back to the limit - the material cover opened. At this point, a workflow is completed, and after loading again, the cutting workflow begins again.

 

Fifth, the installation and debugging of gantry shear equipment, basic operation:

 

1. Each component is in position, connect the hydraulic pipeline, and connect the control circuit. Add a good amount of hydraulic oil.

 

2. Connect to the main power supply. Check the motor running direction, voltage, current, etc.

 

3. Trial run. The gantry cutting equipment supports the button operation of the panel of the operation box and the hand-held remote control operation of the main flow of the cutting work. In manual mode, each component can operate separately, no position correlation, no conflict when there is no material in the material box.

 

Manual mode, operate the mechanical hydraulic function parts. Ensure that the movement is normal and there is no leakage in the pipeline. The limit switch is firmly fixed, the distance between the working face and the metal plate plane of the detection point is suitable (the best distance is 3-5MM), and the function is reliable. In automatic mode, set the cutting length (cutting length or pushing time setting, the unit MS or second, 1 second =100MS), that is, the time of pushing the cylinder once, so as to determine the feeding length. Add or subtract as needed during commissioning.

 

4. Trial production: gantry cutting equipment is in the starting position and filled with materials. Electric control box panel knob, manual automatic automatic position, lubrication release position, heat dissipation release position, material cover as required to place (or no). These functions will be automatically controlled by the PLC according to the working conditions. Press the automatic start (remote control "automatic open"), gantry cutting equipment automatic mode will automatically cut the full container material completed. When finished, return to the starting position to complete a production cycle.

 

Six, gantry cutting equipment to the customer site, by the manufacturer's technical staff guidance installation, commissioning. And do the necessary training for the relevant operators, etc., handed over to the customer operators to operate the production.

 

Seven, gantry cutting equipment maintenance:

 

1. Daily solid and leakage inspection of oil pipeline, joint and other positions. Deal with the problem promptly (tighten and replace the seal ring).

 

2. Check the oil temperature, the workpiece condition of the cooling system, and the motor temperature. The water supply circulation of the water cooling system, the blocking and covering of the heat exchanger of the air cooling system, etc.

 

3. Lubrication of the running parts must be in place, and it is also the focus of daily inspections. Failure to lubricate will cause serious wear or damage to the machine.

 

4. After a certain date of use, you should also check whether the position of the machine is displaced. Find the cause and deal with it in time.

 

5. Electric control box dust, oil, rain. Long time operation in high temperature environment.

 

Eight, in case of problems, find manufacturers. Manufacturer's quality after-sales make you rest assured, happy.

 

 


上一篇: Where is the sc
下一篇: 路友装备浅析—鳄鱼剪与龙门剪有
  • Shandong Luyou renewable resources equipment Co., LTD
  • 地址:Linshu North toll Station, Qingyun Town, Linshu County, Linyi City, Shandong Province, facing south
  • telephone:18253988688(Route manager)